Follow your curiosity

What discovery has been shared with you?

Start with one fact. Explore it, go deeper, then follow whichever branch catches your imagination.

Choose subjects for a surprise

Exploring any topic

Begin your discovery

Your next discovery is one click away.

Choose one or more subjects above, or leave Any Topic selected and let curiosity decide.

Law

The Enforceability of Liquidated Damages Clauses in Construction Contracts

Quick fact

In common law jurisdictions, a liquidated damages clause will be struck down as a penalty if it is 'extravagant and unconscionable' compared to the greatest possible loss that could be anticipated, even if the parties agreed to it freely.

Why this is interesting

You sign a construction contract with a clause that says 'If you're late, you pay $10,000 per day.' But what if the real cost of delay is only $100? Is that clause worth the paper it's written on?

Read the full explanation

Understanding The Enforceability of Liquidated Damages Clauses in Construction Contracts

Imagine you hire a contractor to build a warehouse. The contract says that for every day the contractor is late, they pay you $1,000. This is a liquidated damages clause: it sets a fixed amount that the contractor must pay if they delay. It's like a pre-agreed price for delay. The idea is to avoid the hassle of proving actual losses in court. But what if the actual cost of delay is much less than $1,000? For example, if the warehouse would only generate $200 per day in profit, then $1,000 might be unreasonable. Courts will step in and say that the clause is not a genuine pre-estimate of loss but a 'penalty' designed to punish the contractor. And in contract law, punishing a breaching party is not allowed—the goal is to compensate, not punish. So, if a court determines the clause is a penalty, it will refuse to enforce it. This means the contractor won't have to pay the $1,000 per day; instead, the owner must prove their actual losses in court. The key idea is that a liquidated damages clause must be a reasonable forecast of the likely loss, not a threat to scare the contractor into compliance.

A deeper explanation

The enforceability of liquidated damages clauses rests on a fundamental legal principle: the distinction between a valid pre-estimate of damages and an unenforceable penalty. The rule is that if the clause is a genuine pre-estimate of the loss that would be suffered as a result of a breach, it is enforceable. If it is not a genuine pre-estimate, and instead is a deterrent or punishment, it is a penalty and is void. The leading case in this area is Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79, which established a set of guidelines. The key test is whether the sum stipulated is 'extravagant and unconscionable' in comparison with the greatest loss that could conceivably be proved to follow from the breach. For example, if a construction contract for a factory that would generate $10,000 per day in revenue has a liquidated damages clause of $15,000 per day, that might be reasonable because it covers not only lost revenue but also potential extra costs. But if the clause sets $100,000 per day, that would be considered a penalty. The clause is a penalty if it is designed to coerce performance through a threat of excessive liability. This mechanism has important implications. If a clause is held to be a penalty, the injured party cannot claim the amount stated; they must instead prove their actual damages, which can be a lengthy and costly process. Furthermore, the penalty rule applies even if the parties negotiated the clause at arm's length and were aware of the consequences. The rationale is that the law will not enforce clauses that are oppressive and punish a breach, as this would be contrary to public policy. In construction contracts, this means that contractors and owners must carefully draft the clause to reflect a reasonable estimate of the loss, often with supporting evidence, to ensure its enforceability. The rule also encourages parties to be realistic when assessing potential losses, which promotes fairness and efficiency in contract administration.

Keep FACTREE close

Internet access is required. Updates arrive when you reopen or reload the app. You may need to sign in again in the installed app.